A Phoenix LiveView Gantt chart component: horizontal bars on a time axis, dependency arrows between them, sub-projects with roll-up bars, corner badges, click-to-detail popovers, expand/collapse hierarchy, and a built-in geometry audit.

The gantt/1 component is render-only: you give it events with start/end dates and it draws bars, columns, connectors, and frames. It has no concept of durations, working hours, or scheduling. If your domain has durations + an order + sub-projects but no dates, the optional PhoenixLiveGantt.Layout.sequential/2 helper does that translation for you (sequential waterfall, sub-project span, day-aligned min span) with a pluggable calendar callback — see Laying out from durations.

Installation

def deps do
  [
    {:phoenix_live_gantt, "~> 0.1"}
  ]
end

There are three wiring steps — deps, JS, and CSS. Skipping the CSS step is the most common mistake; the chart renders but library-specific styling is silently missing (see below).

1. JS hooks

The popover, fade-on-open, and auto-scroll-to-today behaviours need the JS hooks. In your app.js:

import "../../deps/phoenix_live_gantt/priv/static/assets/phoenix_live_gantt.js"

let liveSocket = new LiveSocket("/live", Socket, {
  hooks: { ...window.PhoenixLiveGanttHooks, ...myHooks }
})

The bars render without the hooks, but clicking a bar/label won't open its popover and the today-button / auto-scroll won't work.

2. CSS / Tailwind (required)

PhoenixLiveGantt ships no stylesheet. Its visuals are Tailwind utility classes that live inside the component's template (.ex source in deps/phoenix_live_gantt). Tailwind only emits CSS for classes it can see, so you must add the package to your content sources, or library-specific classes (the sub-project pattern-fill, text-[0.6rem] connector labels, non-working-day shading, badge sizing, …) get purged and the chart looks subtly broken.

Tailwind v4 — add an @source to your app.css:

@import "tailwindcss";
@source "../../deps/phoenix_live_gantt/lib";

Tailwind v3 — add a glob to content in tailwind.config.js:

module.exports = {
  content: [
    "./js/**/*.js",
    "../lib/my_app_web/**/*.*ex",
    "../deps/phoenix_live_gantt/lib/**/*.*ex"
  ]
}

PhoenixLiveGantt uses daisyUI semantic color tokens (bg-primary, text-base-content, bg-success, …). daisyUI isn't required — every color is overridable per attr (see bar_default_color_class and friends) — but the defaults assume those tokens resolve to something.

Quick check that CSS is wired: a sub-project's roll-up bar should show a diagonal hatch pattern and connector labels should be legible. If bars are flat-colored and labels invisible, your content source is missing.

Basic usage

<PhoenixLiveGantt.gantt
  id="project"
  events={@tasks}
  date_range={@range}
  connectors={@connectors}
  zoom={:week}
  today={@today}
/>

A task is a PhoenixLiveGantt.Task struct:

%PhoenixLiveGantt.Task{
  id: "cut-wood",                # unique within the chart; connectors + parent_id reference this
  title: "Cut planks to length",
  start: ~D[2026-04-01],
  end: ~D[2026-04-04],           # EXCLUSIVE — see "Dates → bars" below
  color: "bg-primary",
  assignee: "Sara",
  progress_pct: 60,
  extra: %{}                     # badges, actions, parent_id, per-task overrides
}

date_range is a Date.Range (Date.range(first, last)) for the visible axis. Pass id whenever you use the built-in toolbar (show_header) or auto-scroll, and always when more than one chart shares a page — DOM ids and JS dispatches are namespaced by it.

See PhoenixLiveGantt.gantt/1 for the full attr list (there are many styling hooks, all with sane defaults) and PhoenixLiveGantt.Task for all task fields.

Dates → bars

How a task's start/end become a bar — worth reading once, because end being exclusive trips people up:

  • end is exclusive. A bar covers [start, end). A task that occupies just April 1 is start: ~D[2026-04-01], end: ~D[2026-04-02]. If end is nil, PhoenixLiveGantt.Task.effective_end/1 fills it in: start + 1 day for a Date, +30 min for a DateTime/NaiveDateTime.
  • Milestones. When end <= start (zero duration) the task renders as a diamond instead of a bar. A nil-end task with no children is a milestone too.
  • Bar width is honest by default (min_bar_px: 0): a bar is exactly as wide as its duration, so a task too short to see at the current zoom is a hairline (and gets a "too small to see" marker — see tiny_bar_px). Set min_bar_px to e.g. 4 to floor every bar to a visible sliver.
  • Out-of-range events are dropped, not clipped. A task entirely outside the visible window isn't rendered; instead it's counted into the "← N earlier / N later →" edge indicators. Wire on_show_earlier / on_show_later to let users widen the range.
  • Zoom (:min5 / :min15 / :hour / :day / :week / :month) only changes column grouping and pixels-per-day; it never changes which events are in range. The sub-day zooms render intra-day detail from DateTime / NaiveDateTime starts.

Sub-projects (hierarchy + roll-up)

Any event becomes a child of another by setting extra.parent_id to the parent event's id. The parent renders as a roll-up bar spanning its descendants, with an expand/collapse chevron and a framed band across both columns.

Three things that aren't obvious and cost me time when I built the first consumer — they're the rules to internalize:

  1. Always include every descendant in events. The library decides an event is a sub-project (and draws the chevron) by finding other events that point at it via parent_id. It then hides the children of collapsed parents itself. So you emit the full tree every render and let expanded control visibility — do not add children only when expanded, or a collapsed parent has nothing pointing at it and never gets a chevron.

  2. Let the parent's dates roll up — pass start: nil, end: nil. A sub-project parent with nil dates is auto-sized to span its descendants' min start / max end. If you instead give the parent explicit dates (e.g. from a rolled-up duration), the library uses those and the children can visually spill outside the bar — you'd have to size the parent to its children yourself. Nil-and-let-it-roll-up is almost always what you want.

  3. on_toggle_expand fires with the param key event-id (hyphen, from phx-value-event-id), and you own the expanded set:

    # render
    <PhoenixLiveGantt.gantt
      events={@events}
      date_range={@range}
      expanded={@expanded}                 # MapSet | list | :all | nil
      on_toggle_expand="toggle_subproject"
    />
    
    # the handler — note the hyphenated key
    def handle_event("toggle_subproject", %{"event-id" => id}, socket) do
      expanded = socket.assigns.expanded
      expanded =
        if MapSet.member?(expanded, id),
          do: MapSet.delete(expanded, id),
          else: MapSet.put(expanded, id)
    
      {:noreply, assign(socket, expanded: expanded)}
    end

expanded accepts a MapSet, a plain list, :all (everything expanded), or nil (all collapsed). Connectors that point at a hidden child are automatically retargeted to its nearest visible ancestor, so arrows never dangle.

Laying out from durations

If your data has durations rather than dates, PhoenixLiveGantt.Layout.sequential/2 turns it into the dates gantt/1 wants — so you don't hand-roll (and re-bug) the waterfall + sub-project-span + day-alignment yourself:

layout =
  PhoenixLiveGantt.Layout.sequential(tasks,
    start: ~D[2026-06-01],
    id: & &1.id,
    parent_id: & &1.parent_id,      # nil = top-level; others nest
    duration: & &1.hours,           # opaque — only your :advance interprets it
    order: & &1.position,
    advance: fn start_date, hours, task ->
      # your calendar: weekends, working hours, holidays — all live here
      MyApp.Calendar.add(start_date, hours, task)
    end
  )
# => %{id => %{start: ~D[...], end: ~D[...]}}

events =
  Enum.map(tasks, fn t ->
    %{start: s, end: e} = layout[t.id]
    %PhoenixLiveGantt.Task{id: t.id, title: t.title, start: s, end: e,
                    extra: %{parent_id: t.parent_id}}
  end)

It works entirely in Dates, so each item gets at least a one-day slot (:min_span_days, default 1), siblings never overlap, and a sub-project's bar always spans its laid-out children. The business calendar is yours (the :advance callback); the library stays domain-agnostic. It does not do dependency-driven scheduling, critical path, or resource leveling — supply your own dates for those.

Connectors

Dependency arrows are plain maps referencing event ids:

%{from: "cut-wood", to: "assemble", type: :fs, critical: true, label: "2d lag"}
  • type:fs (finish-to-start, default), :ss, :ff, :sf.
  • A connector whose from/to isn't a visible event id is silently skipped (e.g. it points outside date_range).
  • A backward / impossible schedule (the dependent is laid out earlier than the constraint allows) is auto-detected and drawn in the invalid style (dashed, error color) — a free correctness check on your date mapping.
  • critical: true draws it in the critical style; label annotates the line.

Debugging

Gotchas

The short list of things that bite, collected from building the first consumer:

  • No CSS content source → chart renders but library-specific classes are purged. (See CSS step above — the #1 issue.)
  • end is exclusive → a one-day task needs end = start + 1, not end = start (which is a milestone diamond).
  • Sub-project children must always be in events → emit the full tree; expanded controls visibility. Adding children only when expanded breaks the chevron.
  • Give sub-project parents nil dates → so they roll up to span their children. Explicit parent dates can let children spill outside the bar.
  • on_toggle_expand param is "event-id" (hyphen), not "event_id".
  • id is required with show_header / auto-scroll, and whenever two charts share a page (ids + JS dispatches are namespaced by it).
  • The JS bundle is effectively required. The LgBarPopover / LgAutoScroll hooks ship in priv/static/assets/phoenix_live_gantt.js (registered as window.PhoenixLiveGanttHooks). enable_hooks (default false) gates BOTH hooks; if you turn it on without registering the bundle you'll get "unknown hook" console errors. The popover and scroll-to-today need it.
  • Sub-project chevrons use heroicons (hero-plus-mini / hero-minus-mini). Those classes exist only if your app has the heroicons Tailwind plugin (the default in Phoenix ≥ 1.7, but not universal). No plugin → no chevron glyph.
  • dir="rtl" sets the attribute but the geometry is LTR-only — bars, the time axis, and connectors still run left-to-right. RTL text in labels renders fine; the chart layout does not mirror.

Large charts

Horizontal geometry is pure CSS (percent positions, no measurement), so wide timelines are cheap. The cost is the connector router: collision avoidance is roughly O(tasks) per connector, and a chart re-renders/serializes its full HTML over the LiveView socket. A few hundred tasks with dependencies at a fine zoom produces multi-MB diffs and second-scale re-renders. To keep big charts snappy:

  • Set avoid_collisions: false (component attr, or per-connector) to skip the obstacle pass — connectors may cross unrelated bars but routing is much cheaper.
  • Narrow date_range (or pass a window_start/window_end) so only the relevant slice renders; out-of-range tasks become cheap edge-indicator counts.
  • Prefer coarser zooms (:week / :month) for overview; reserve :day and the sub-day zooms for focused windows.

Status

Pre-1.0; API may shift. See CHANGELOG for breaking changes.